A test of temporary generator power at the campus Data Center didn’t go well, and the Data Center was shut down at about 11am this morning. This affects a number of IRIS services, such as lists.eecs (mailing lists) and IRIS apps (account and system registration requests), and is also having an impact on wifi authentication.
Please see the Berkeley Status Dashboard for updates: https://berkeley.statusdashboard.com/event/192049/
UPDATE
[2024-02-08 | larsrohr ]
Campus continues to restore power to systems at the Data Center. We believe that all IRIS services are back to normal at this time. Any further updates can be found at the URL above.
Resolved as of 2024-02-08 3:30pm