IRIS is upgrading all edge network switches in Cory, Soda, & BWRC. The new switches will provide gigabit Ethernet to all wired network connections.
During the upgrade, most devices will experience only one or two brief disruptions of a few seconds each as cables are moved during the scheduled maintenance window.
There is a possibility that physical constraints will force extended downtime in some areas; we will contact sysadmins of registered systems in advance.
The upgrade will take many weeks and this schedule will evolve and change. Please revisit this announcement to find the current schedule.
### Schedule
Dec 14: DONE Soda Instructional datacenter
Dec 21: DONE Soda 2nd floor Instructional Labs
Jan 14: DONE Soda Hall 3rd floor northeast – 3B-*
Jan 11-19: DONE Cory 1st floor – 115-*
Jan 21: DONE Cory datacenter – 165-*
Jan 26: DONE Soda 7th floor – 7A-*
Feb 4: DONE Soda 4th floor south – 4A-*
Feb 4: DONE Soda 4th floor north – 4B-*
Feb 18: DONE Soda 6th floor – 6A-*
Feb 23: DONE Soda 5th floor south – 5A-*
Feb 25: DONE Soda 5th floor north – 5B-*
Mar 17: DONE Cory 5th floor – DOP Center – 550A-*
Apr 1: DONE Cory 5th floor – 561-*
Apr 8: DONE Cory 4th floor – 405-*
Apr 15: DONE Cory 3rd floor part 1 – 315-*
Apr 20: DONE Cory 3rd floor part 2 – 315-*
Apr 26: DONE Soda Hall 3rd floor southwest – 3A-*
May 18: DONE Cory 2nd floor – 208-*
Jul 12-14: DONE BWRC